NB Power settlement for Point Lepreau project could lead to lower rates: CEO
FREDERICTON — New Brunswick’s Crown-owned utility has reached a settlement with insurers who underwrote an all-risk policy for refurbishment of the Point Lepreau nuclear generating station, which took three years longer than planned and cost a billion dollars more than budgeted.
NB Power CEO Gaetan Thomas did not disclose the terms of the settlement Monday, citing a confidentiality agreement.
However, he said the proceeds from settlement will allow the utility to seek a lower electricity rate increase “for all New Brunswickers.”
In a 2018-19 rate application, the utility had asked the province’s Energy and Utilities Board to raise rates by about two per cent.