Street sweepers have been on the roads in Prince Albert since the beginning of this week, clearing sand and debris in the downtown and ensuring equipment is ready to start full operations Monday at 5 a.m.
Roadways Manager Brent Kennedy told paNOW the sweeping schedule is the same as snow clearing, with crews starting with priority one arterial roads.
Weather permitting, they should be into priority four, residential areas, by the end of May or the beginning of June, with the entire operation being complete in six to seven weeks.
“A very light shower is okay because we do wet down the roads with our water truck anyway,” Kennedy said. “But if it’s a heavy rain and there’s water then it just turns into mud so we’re basically shut down.”