‘Big dig’ to take 3 months to finish
Construction work on Prince Albert’s Second Avenue West ‘big dig’ could begin as early as the week of June 8, and is expected to last for 12 weeks.
On Monday, city council approved a close to $1.5 million tender for the project to Mi-Sask Industries. The City plans to meet with the contractor to discuss detours as well as lane restrictions.
Capital projects manager Wes Hicks told members of council that Second Avenue West will always be open and traffic will be limited to one lane in each direction between 12th Street West and 15th Street West.
He said the contractor plans to have crews work 10-hour days over the course of six days per week, with no work taking place on long weekends. Crews will work from 7 a.m. to 5:30 p.m. and they will work longer hours if the weather causes the project to fall behind schedule.